Summary
Commissioners flagged that Colet Creek Road has only about two inches of asphalt and can't handle heavy reactor deliveries. Valar committed to upgrades in the short term and a new access road off the airport road through BLM land long term.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 12, 2026.
Impact analysis
Valar agreed to be responsible for road damage and improvements through the road encroachment permit process.
Residents who use Colet Creek Road if improvements and the new access route are delivered.