Critical PriorityRoadsopen

Interchange infrastructure funding and WIFIA deadline

Summary

Interchange design is about 80% complete with drainage issues being worked out, and UDOT won't let the city remove steel pipe from Main Street drive approaches, frustrating residents. The project has a new manager, Steven Loveland.

At a glance

Total mentions
5
Last 30 days
0

Discussed at 2 meetings in the last 60 days; most recently Sep 30, 2026.

Impact analysis

💰Financial impact

$47,000 secured for approved drive-approach curb work; interchange costs carried by UDOT.

✅Who benefits

Commuters and Main Street businesses once the interchange and street work wrap up.

⚠️Who could be affected

Main Street residents whose drive approaches still have steel pipe UDOT won't let the city remove.

Mentions & discussions (5)

MeetingSep 30, 2026

City Council - Sep 30, 2026

UDOT plans to bid the I-15/Payson Parkway interchange in February 2027, and the city must hand over about $14–15 million for the infrastructure at that time. The city is rushing its WIFIA federal loan application; if it falls through, state infrastructure funding set aside by the legislature is a backup. PRI would repay the city through impact fees.

MeetingSep 16, 2026

City Council - Sep 16, 2026

The big interchange project cleared its final design review. Bidding starts early 2027, construction next year — but the stretch from I-15 back to Main Street probably won't make the cut due to budget.

MeetingSep 16, 2026

Payson City Council Meeting — September 16, 2026

UDOT's final design review is done and construction starts in 2027, with bidding in early 2027. A couple of holdout property owners may face eminent domain, and the stretch from I-15 back to Main Street likely won't get built due to funding.

MeetingMay 6, 2026

City Council - May 6, 2026

Interchange design is about 80% complete with drainage issues being worked out, and UDOT won't let the city remove steel pipe from Main Street drive approaches, frustrating residents. The project has a new manager, Steven Loveland.

MeetingFeb 18, 2026

City Council - Feb 18, 2026

UDOT says the new interchange could break ground late 2026 or spring 2027, but the 800 South interchange upgrade is unfunded and needs to move from phase two to phase one in the regional plan. A public open house is set for March 11.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Payson City

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.