Rising power bills and the EDAM market
Power bills jumped this summer due to the new regional EDAM market, a broken Nebo plant turbine, high heat driving up usage, and construction delays on the city's new power plant. Fixes are coming — the turbine returns around Christmas, a costly contract ends in April 2027, and the new plant should stabilize costs — but residents on fixed incomes are feeling it now, with the shutoff list at 67 customers.
Utility Billing Fairness Concern
Customers on budget-billing now need 12 months of on-time payments to join, and amounts recalculate once a year. The city will publicize the change so nobody gets accidentally kicked off.
Racetrack to Firehouse Transmission Line Easement / Eminent Domain
The city authorized using eminent domain, if needed, to grab the last easement for the transmission line serving southern Payson. Homeowner Jennifer Mann asked the council to wait for her independent appraisal, but the council moved forward while negotiations continue.
Electric vehicle charging capacity
Payson has only one slow EV charger because the city lacks the electrical capacity and substations for fast chargers. Board members noted strategic chargers could draw road-trippers to shop and eat locally.
Proposed Rocky Mountain Power Transmission Line
City staff attended a Rocky Mountain Power open house about a proposed 345-kV transmission line that would run through Payson along the Sharp railway line. Administration has real concerns about its location and will keep the council updated as meetings proceed.
New city power plant online
Payson's power plant finished construction and started running August 1 after two and a half years of work. The director noted data centers, even off-grid ones, can strain the natural gas supply.
Water conservation plan update
The consent-agenda update keeps rates tiered but raises no fees. Staff highlighted ongoing water audits, a planned conservation demonstration garden on American Way, and rebate eligibility through Central Utah Water Conservancy.
Series 2026 sewer bond financing
The council authorized $5 million more in sewer revenue bonds to finish the sewer plant, on a 4-1 vote. Sewer rates currently fund debt service; 64% of sewer revenue already goes to debt.
Future power substation site purchase
The city can buy land at 1350 N Arrowhead Trail for a future substation, but the deal hinges on a separate annexation that staff expects to fail at Planning Commission — Smith voted no over the contingencies.
Hydropower diversification deal
Payson locked in a five-year contract to buy hydropower from the Strawberry Water Users Association plants in Spanish Fork and Payson Canyons — fuel-free, inflation-free power that diversifies the city's energy portfolio.
Lead and galvanized water line replacements
EPA rules require the city to identify lead, galvanized, and copper service lines. The city is replacing its side of the meter; homeowners must replace lines from the meter to their houses — staff will help residents figure out what they have.